DeVere St. David's Hotel, Cheshire

DeVere St. David's Hotel, Cheshire

As part of their nationwide refurbishment programme the Village Hotel Group and ISG Regions engaged us with a remit to create a rooftop tunnel to escort customers betweent wo parts of the existing St David's Hotel.

Following an intrusive site survey we designed the corridor using a Kemper finish to the main roof and walls and aluminium doors and windows all supported from our lightweight cold formed steel structure.

All works were carried out during normal hotel operations and were completed in a two week period.

Topek Project Value £125k

 

 